| Most of the cement ceiling panels are in place |
| The bedroom wing |
It consists of several layers.
Layer 1
Concrete 9mm ceiling boards are nailed to the trusses. We pre-painted the ceiling boards on one side to make the final painting less of a hassle.
Layer 2
Then purlins are nailed to the trusses through the ceiling boards and a 70mm thick insulating blanket is laid between the purlins.
Layer 3
On top of all that is laid a layer of sisalation which acts as a vapour barrier and has insulating properties as well.
Layer 4
Finally the layers are covered with Chromadek sheeting which has the colour of the roof (dove grey) baked into the surface of the metal. A capping piece is fixed to the apex of the roof.
| Gives one an idea of what it will look like from the inside |
We will also be able to install the Solar Geyser and Solar power panels.
The next two weeks should be quite eventful.
| This in not an old man,s Meccano set. It will become a Battery Rack for the deep cycle batteries |
Taking shape, looking GOOD.....