The trenches have been dug and 3 x 10 mm reinforcing bars joined by cross bars (10mm) at 2 metre intervals has been laid in each of the 8 trenches. We have lifted these of the base using 50 mm spacers. On Thursday afternoon we are going to pump concrete into these footings. Then the plinths have been built we will scrape out each section to a uniform depth of 200mm and use a whacker to stabilise the surface.
The surface is pretty stable as it is as we are down to the sub strata which contains a lot of stone and rocks

Then its layers of ant poison, heavy duty plastic, polystyrene, 50mm spacers and ribbed weldmesh.
And we fill it all up with pumped concrete.
Probably by Wednesday 25th June.